Senate orders contractor to speedily complete N30bn NASS project

A file photo of lawmakers in the Senate chamber of the National Assembly in Abuja.

The Senate Committee on Federal Capital Territory (FCT) has ordered Visible Concept, the construction firm handling the N30 billion renovation work at the National Assembly to speedily complete the projects.

Sen. Smart Adeyemi, Chairman of the senate Committee, gave the order at an on the spot assessment of the projects by members of the committee with the Executive Secretary, Federal Capital Development Authority (FCDA) , Shehu Ahmad.

The News Agency of Nigeria (NAN) recalls that the FCDA had in March due to serious dilapidation of the national assembly complex, awarded contracts for rehabilitation of critical segments of the complex.

The segments included the hallowed chambers of the senate and the House of Representatives, the Dome in the White House as well as construction of office of the National Assembly Service Commission ( NASC) and Library at the cost of N30 billion.

Adeyemi who noted that though the renovation works being carried out at both chambers were commendable, said however, that the slow pace of work was very worrisome.

He said that except for miracle, the January 2023 deadline for delivery of transformed hallowed chambers was no longer feasible.

“This project must not be abandoned in anyway. The hallowed chambers are expected to be completed and delivered by the end of January 2023.

“But the level of work seen here today is not pointing at that which to us, is a threat to our legislative duties and functions.

“Non-completion of this project at designated times is even a threat to democracy itself because we don’t want the incoming government to inherit it as an abandoned one.

“So, this committee wants to know the challenges confronting the contractors as regards expeditious execution of the projects,” he said.

Adeyemi also told the executive secretary of FCDA to get in touch with the minister for more funds for the contractors.

`As executive secretary of FCDA and Chief of Staff to the Minister, you have heard the contractor. Please give them more money for this project because we don’t want to hand over problems to the incoming government.

“Even if it is bond to be taken from a bank, let it be done for timely completion of the project please.

“For us in the national assembly, we want well transformed hallowed chambers to be handed over latest by April 2023,” he said.

On his part, the Site Engineer, Visible Concept, Mr Tajudeen Olanipekun asked for more funds to complete the project in good time.

He said that fluctuations in the value of Naira to the U.S. dollar had been problematic for them in importation of required materials and equipment, coupled with the need for more mobilisation funds from the FCDA.(NAN)

DISCLAIMER

The OPINION / COLUMN is authored by independent contributors to the National Accord Newspaper. While contributors adhere to our editorial guidelines, they are not employed by the National Accord Newspaper. The perspectives and opinions expressed herein are solely those of the author and do not represent the views of the National Accord Newspaper or its staff.

Be the first to comment

Leave a Reply

Your email address will not be published.


*