FEC approves upward review of injection substation contract for improved electricity supply in Abuja

FCT Minister, Malam Muhammad Musa Bello

In a bid to improve power supply in the FCT, the Federal Executive Council (FEC) has approved the upward review of contract for the construction of 33/11KV injection substation for Life Camp, Gwarinpa 1 District.

The approval was granted following a Council presentation to this effect, by the FCT Minister, Malam Muhammad Musa Bello on Wednesday, 22nd June 2022.

A statement issued on Wednesday by the Minister’s Chief Press Secretary, Mr. Anthony Ogunleye, said the upward review will increase the substation’s electricity capacity from 2x15MVA to 3x15MVA and cater for the current and future power load requirements for Life Camp and environs.

Executive Secretary, Federal Capital Development Authority (FCDA), Engr. Shehu Hadi Ahmed said that the project became necessary owing to rising population growth, increased economic activities in the District, overlap in construction period, as well as changes in foreign currency exchange rates, amongst others.

Explaining the necessity for the project, Engr. Ahmad said: “There is supposed to be provided an injection substation, and in some cases, two substations for every District. In this case, Gwarinpa 1 District, which houses Life Camp has been on a temporary supply extended from another District, particularly Jabi District.

“This is because we have not developed the injection substation for Gwarinpa 1 District. So this contract provides for three number of 15KVA heavy duty transformers. Two will be working at any given time, while one will be on standby.

Speaking on the impact of the project, he said: “Life Camp gets its power supply from Jabi District; this will be discontinued following the completion of the project and will ultimately improve power supply in Jabi.

He also explained that on completion, the injection substation will also cater for the electricity needs of the entire Life Camp and Gwarinpa 1 District.

The contract which was awarded to Messrs Wireteks International Ltd at the sum of N1,640,406,462.26 has a completion period of 15 months.

DISCLAIMER

The OPINION / COLUMN is authored by independent contributors to the National Accord Newspaper. While contributors adhere to our editorial guidelines, they are not employed by the National Accord Newspaper. The perspectives and opinions expressed herein are solely those of the author and do not represent the views of the National Accord Newspaper or its staff.

Be the first to comment

Leave a Reply

Your email address will not be published.


*